The Canal del Dique restoration project, a key infrastructure and environmental initiative in Colombia, faces new daily navigation restrictions and a significant fiscal freeze. Starting July 27, transit is limited to 8 a.m. to 4 p.m. for one year to facilitate safe dredging Source: portafolioco. Meanwhile, in January, the government froze 636,000 million pesos in future budget allocations, stalling flood protection works for 19 municipalities Source: eltiempoco.
The total project investment is $3.25 billion, with a pre-operational phase extending to March 2027 Source: portafolioco. The freeze has created uncertainty for communities that have awaited action since severe floods in 2010 affected over 170,000 people Source: eltiempoco. Progress is underway: 76% of required land parcels are identified as public, and over 2.5 million cubic meters of sediment have been removed Source: portafolioco.
The ANI is conducting the Environmental Impact Study required by ANLA, with a budget of $75.882 billion allocated for this component Source: portafolioco. The project envisions 95 civil works across 117.5 km, including hydraulic complexes and fish passage systems, to restore ecosystems and protect communities Source: eltiempoco. Local leaders expect the incoming government to provide renewed support and accelerate the stalled works.
“Desde el 27 de julio, y durante todo un año, el tránsito por el Canal del Dique operará únicamente entre las 8:00 a.m. y las 4:00 p.m.”
“En enero pasado, el Gobierno Nacional congeló $636.000 millones asignados con vigencias futuras para la restauración del canal.”
“Pescadores, agricultores y familias asentadas en la ribera esperan desde hace 15 años acciones concretas tras las graves inundaciones de 2010, que afectaron a más de 170.000 habitantes de Atlántico y Bolívar.”
“La ANI adelanta el Estudio de Impacto Ambiental que exige la Autoridad Nacional de Licencias Ambientales (ANLA) antes de aprobar las obras civiles.”