The Government of Mexico City has begun a major hydraulic infrastructure project to combat recurrent floods in the eastern borough of Iztapalapa, particularly along Calzada Ignacio Zaragoza and Santa Martha Acatitla. The total investment is 1.8 billion pesos, with 1.5 billion allocated to drainage infrastructure and 300 million to water management projects. Source: Infobae
Both works are scheduled for completion in 2025: the storm‑tank network by 14 August and the collector by October. However, the storm tanks were originally due in June but faced a one‑month delay because of the early rainy season. Source: Excélsior (aceleran obras) The project will directly benefit 32,700 inhabitants of Santa Martha Acatitla and improve traffic for , with indirect benefits for 1.8 million commuters from the State of Mexico. Authorities assure that neither Metro Line A nor vehicular circulation will be interrupted during construction.
“las autoridades iniciaron una estrategia integral que contempla una inversión de mil 800 millones de pesos en la demarcación, de los cuales mil 500 millones se destinan a infraestructura de drenaje y el resto a proyectos de gestión del agua.”
“Con un avance de obra del 45 por ciento, la red de nueve tanques tormenta que se construye debajo de la lateral de Calzada Ignacio Zaragoza... deberá quedar lista el 14 de agosto”
“El nuevo colector trabajará de manera conjunta con la red de tanques tormenta que actualmente se construye... infraestructura que permitirá regular otros cuatro mil 500 litros de agua de lluvia”
The entire system is expected to be fully operational by the 2027 rainy season. Source: Infobae
“Las lluvias que se adelantaron desde los primeros días de mayo, complicaron el calendario de ejecución, hablamos con la empresa encargada para acelerar los trabajos y cumplir con las nuevas fechas de entrega”